| Foundation forms are creeping around the basement. |
![]() |
| This is what I call the south porch, but I don't know if it will eventually be an entrance from the underground parking garage or not. |
![]() |
| This view of the west side from the construction cam shows the foundation forms being built under the towers. |
![]() |
| Foundation forms aren't being constructed beneath the two east towers. I don't think it's because those two towers will be stairwells, but because the basement cannot extend east. |
![]() |
| This is a view from the cam of the center of the north side foundation. Notice that the Jacobsen crews have begun building the exterior forms. It is easy to see that the foundation is being built between the piers. Once the tabernacle rests on the new foundation, the piers can be cut away, at least on the inside. |
![]() |
| I won't be able to take interior pictures of the basement much longer. |
![]() |
| This is a view of the interior side of the south foundation form. |
![]() |
| This view of the north lot shows dry concrete after the big pour last Friday. |
![]() |
| This view of the west side shows the wide-flange columns which were being worked on last week. Today you can see that more than half have been cut off at ground level. |
![]() |
| This view of the west lot shows the walkway from Center Street, which appears to be shored up as it approaches the site. |
![]() |
| Wells are in place along the south wall of the west side. Remember that the entrance to the underground parking is in the center of this picture. |
![]() |
| Since I usually use my zoom lens here, you might not have appreciated how big the south lot really is. |